Building Project Events

Project Status Update - January 21, 2026
- Scope of work: Simultaneous construction of two buildings plus infrastructure required for Phase 1 of the campus construction.
- Current stage: Phase 1 of the Del Puerto Ambulance and Administration Center and Combined Clinic – 50% schematics completed.
- Next Stage: RFQ Release March 2026
- Square footage of new construction: DPAC 19,000 and Combined Clinic 34,000
- Number of Stories: One
- Framing Type: Steel
- Contract Type: Progressive Design-Build
- Target Bid Date: RFQ to be released at the end of March 2026
- Target Construction Start Date: Sept 2026
- Target Completion Date: Sept 2028
Tentative Building Schedule
- Break ground on DPAC & Combined Clinic – 2026
- Completion of DPAC & Combined Clinic – 2028
- Senior Living and/or Medical Office Building (MOB)~2028 to 2032
- Independent Senior Living ~2030
- Assisted Senior Living ~ 2033
- Acute Care Hospital Emergency Department, and Parking Structure ~ 2035-40
- Memory Care and Skilled Nursing ~ 2035-40
Untimed Projects:
- Commercial Development at 9th & Sperry
- Residential Development – Townhomes
- Mixed Use Development
- Retail Development at 9th & Las Palmas