Strategic Timing Adjustment - UPDATE May 26, 2026

  • Scope of work: Simultaneous construction of two buildings plus infrastructure required for Phase 1 of the campus construction.
  • Current stage: Phase 1 of the Del Puerto Ambulance and Administration Center and Combined Clinic – 50% schematics completed.
  • Next Stage of Phase 1:
  • Square footage of new construction: DPAC 19,000 and Combined Clinic 32,000
  • Number of Stories: One
  • Framing Type: Steel
  • Contract Type: Progressive Design-Build
  • Target Bid Date: January 2027
  • Target Construction Start Date: July 2028
  • Target Completion Date: February 2030

Tentative Building Schedule - UPDATED May 26, 2026

  • Break ground on DPAC & Combined Clinic – 2028
  • Completion of DPAC & Combined Clinic – 2030
  • Senior Living and/or Medical Office Building (MOB)~2030 to 2034
  • Independent Senior Living ~2032
  • Assisted Senior Living ~ 2034
  • Memory Care and Skilled Nursing ~ 2035-40
  • Acute Care Hospital Emergency Department, and Parking Structure ~ 2040-45

Untimed Projects:

  • Commercial Development at 9th & Sperry
  • Residential Development – Townhomes
  • Mixed Use Development
  • Retail Development at 9th & Las Palmas