Building Project Events

Strategic Timing Adjustment - UPDATE May 26, 2026
- Scope of work: Simultaneous construction of two buildings plus infrastructure required for Phase 1 of the campus construction.
- Current stage: Phase 1 of the Del Puerto Ambulance and Administration Center and Combined Clinic – 50% schematics completed.
- Next Stage of Phase 1:
- RFP Project Manager Release December 2026
- RFQ Progressive Design Build Release January 2027
- Square footage of new construction: DPAC 19,000 and Combined Clinic 32,000
- Number of Stories: One
- Framing Type: Steel
- Contract Type: Progressive Design-Build
- Target Bid Date: January 2027
- Target Construction Start Date: July 2028
- Target Completion Date: February 2030
Tentative Building Schedule - UPDATED May 26, 2026
- Break ground on DPAC & Combined Clinic – 2028
- Completion of DPAC & Combined Clinic – 2030
- Senior Living and/or Medical Office Building (MOB)~2030 to 2034
- Independent Senior Living ~2032
- Assisted Senior Living ~ 2034
- Memory Care and Skilled Nursing ~ 2035-40
- Acute Care Hospital Emergency Department, and Parking Structure ~ 2040-45
Untimed Projects:
- Commercial Development at 9th & Sperry
- Residential Development – Townhomes
- Mixed Use Development
- Retail Development at 9th & Las Palmas